This page was exported from Actual Test Materials [ http://blog.actualtests4sure.com ] Export date:Fri Nov 15 22:04:50 2024 / +0000 GMT ___________________________________________________ Title: [Feb 19, 2023] Fully Updated Dumps PDF - Latest PRINCE2-Foundation Exam Questions and Answers [Q83-Q103] --------------------------------------------------- [Feb 19, 2023] Fully Updated Dumps PDF - Latest PRINCE2-Foundation Exam Questions and Answers 100% Free PRINCE2-Foundation Exam Dumps to Pass Exam Easily from Actualtests4sure NO.83 Which is an objective of the Managing a Stage Boundary process?  Understand what has gone well and what can help the next stage  Review and approve the next Stage Plan  Assure the Project Board that all project products have been completed and approved  Prepare an Exception Report to advise the Project Board of a forecast deviation from tolerance NO.84 Which is a true statement about PRINCE2 event-driven controls?  Event-driven controls take place at predefined periodic intervals  Event-driven controls are produced at the frequency defined in a Work Package  Event-driven controls are used for decision making  Checkpoint Reports are event-driven controls Section: Volume BNO.85 Which does the Executive need to ensure is in place before the project is initiated?  All Work Packages are authorized  An understanding of how the project will contribute to corporate objectives  The Project Plan has been approved  The Project Initiation Documentation is complete NO.86 Which of the following statements about quality assurance and Project Assurance is true?  Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board  Project Assurance is independent of the Project; qualityassurance is only independent of the Project Manager  Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board  Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization NO.87 Which is an objective of the Starting up a Project process?  Identify who will be responsible for creating the Project Plan  Agree how the project will be monitored and controlled after initiation  Authorize the Project Manager to proceed with the initiation stage  Agree how issues and changes will be identified, assessed and controlled NO.88 Which product identifies how often stakeholders require information?  Communication management approach  Quality management approach  Change control approach  Risk management approach ExplanationReferencehttp://prince2.wiki/Communication_Management_Strategy_Template#Content_of_the_Communication_ManageNO.89 Which of the following is NOT part of quality control?  Maintaining the documentation that records the approval of products  Checking that the project’s direction and management are adequate for the nature of the project  Obtainingacceptance of the project product from relevant stakeholders  Implementing the relevant quality methods and responsibilities NO.90 Which is a purpose of a Project Brief?  Enable the assembly of the project mandate  Describe the reporting requirements of the various layers of management involved with the project  Describe how changes to products will be controlled  Provide a solid basis for the initiation of the project NO.91 What should the benefits management approach define?  What actions will be taken to ensure the project’s outcomes are achieved  What will be used to record the effectiveness of the project’s approaches  How the project has progressed against its plans  The suitability of the project management team structure Section: Volume BNO.92 Which process ensures focus on the delivery of a stage’s products and avoids uncontrolled change?  Directing a project  Managing a stage boundary  Controlling a stage  Starting up a project Explanation/Reference:Reference https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-controlling-a- stage-process-in-prince2NO.93 Which is assumed to be a supplier’s responsibility in the PRINCE2 customer/supplier environment?  Specify the desired result  Provide the resources and skills to deliver the desired result  Pay for the project  Specify the benefits of the project NO.94 Which statement about applying the ‘tailor to suit the project’ principle is CORRECT?  PRINCE2 can be tailored to be used with any type of project  A technically complex project should NOT tailor PRINCE2  The tailoring of PRINCE2 is MOST appropriate for agile projects  A project which is part of a programme should NOT tailor PRINCE2 NO.95 Identify the missing word(s) in the following sentence.The ‘controlling a stage’ process is used to manage and control each [ ? ] of a project.  delivery step  benefit  delivery stage  team plan NO.96 According to PRINCE2, why might there be more than one business case for a project?  There may be more than one management stage in the project  The project may be in a commercial environment with a number of suppliers  There may be more than one work package being delivered in the project  The project may be in a programme environment Explanation/Reference:Reference https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/NO.97 How many tasks does the product-based planning technique describe?  One  Two  Three  Four Section: Volume BNO.98 Which enables the project’s products and all interdependencies to be clearly identified and documented?  Product breakdown structure  Quality Management Strategy  Product-based planning technique  Quality review technique NO.99 Which is a purpose of the ‘initiating a project’ process?  To decide if it is worthwhile to initiate a project  To decide on the project approach  To establish solid foundations for a project  To identify the number of work packages required Section: Volume BExplanation/Reference:Reference http://prince2.wiki/Initiating_a_Project#ObjectiveNO.100 What theme provides the justification for the project?  Quality  Plans  Progress  Business Case NO.101 Which is a purpose of the Starting up a Project process?  Provide information so a decision can be made as to whether a project is viable and worthwhile to initiate  Define the means of communication between the project and corporate or programme management  Define the project controls  Record any identified risks in the Risk Register NO.102 Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?  Corporate group  Project Board  Project Assurance  Executive NO.103 Which is an objective of the ‘controlling a stage’ process?  To review the business justification for the project  To replan the current stage when directed  To develop products to defined quality criteria  To produce a learn plan for the work package  Loading … Free PRINCE2-Foundation Exam Questions PRINCE2-Foundation Actual Free Exam Questions: https://www.actualtests4sure.com/PRINCE2-Foundation-test-questions.html --------------------------------------------------- Images: https://blog.actualtests4sure.com/wp-content/plugins/watu/loading.gif https://blog.actualtests4sure.com/wp-content/plugins/watu/loading.gif --------------------------------------------------- --------------------------------------------------- Post date: 2023-02-19 15:37:50 Post date GMT: 2023-02-19 15:37:50 Post modified date: 2023-02-19 15:37:50 Post modified date GMT: 2023-02-19 15:37:50