The PMI Program Management Professional certification validates your ability to manage multiple, related projects and navigate complex activities that span the organizations, functions, geographic regions, and cultures. After earning this certificate, the successful candidates can take up such job roles as a Project Manager, a Program Manager, a Client Success Manager, a Customer Solutions Manager, and an Engagement Manager, among others. The salary rates associated with this sought-after certification range from $93,000 to $142,500 per year, with a median annual salary of $113,124.

 

NEW QUESTION 286
A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project.
What should the program manager do next?

 
 
 
 

NEW QUESTION 287
Which of the following can be an effective tool during quality control to help determine the how the problem occurred?

 
 
 
 

NEW QUESTION 288
Harriet is the program manager of a large program that has a high profile and visibility in her organization. Some of the stakeholders are negative and Harriet needs to work with these stakeholders to address their fears, perceived threats, and concerns about the program. Which communication method is considered to be the best approach for this scenario?

 
 
 
 

NEW QUESTION 289
A program has a BAC of $1,750,000 and is expected to last two years. The program is currently at the third milestone which represents 35 percent of the program work. As it happens, this program has already spent
$620,000 of the budget. Management is concerned that the program may also be slipping on schedule because the program should be forty percent complete by this time. Based on this information which type of performing is present in this scenario?

 
 
 
 

NEW QUESTION 290
Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder’s opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

 
 
 
 

NEW QUESTION 291
You are the program manager for your organization and you’re dealing with several issues about the materials used in the program. Right now, the issues have been assigned to issue owners for resolution in ten days. In the interim, what should you do with the issues?

 
 
 
 

NEW QUESTION 292
You are the program manager for your organization and are working with your program team to create the program scope. Based on the program requirements you have identified the major deliverables of each phase in your program scope. Management has requested that you plan for cost estimating to happen at each phase of the program before continuing the work. Management may elect to cancel the program at the end of each phase based on past performance of the program. What are the reviews of management called at each phase?

 
 
 
 

NEW QUESTION 293
Part of your job as the program manager is to coach the project managers on their duties and goals. One of the project managers, Holly, is having trouble discerning the difference between quality assurance and quality control. She understands that she needs both to help you reach the program goals. Which statement best describes quality control for a project within your program?

 
 
 
 

NEW QUESTION 294
You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?

 
 
 
 

NEW QUESTION 295
Which of the following is NOT true regarding the program work breakdown structure (WBS)?

 
 
 
 

NEW QUESTION 296
To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized.
What should the program manager do?

 
 
 
 

NEW QUESTION 297
In your program you must adhere to Six Sigma as part of your organization’s enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?

 
 
 
 

NEW QUESTION 298
You are the program manager for your organization and you’re trying to determine if you buy or build a software solution for your organization. If you build the solution it’ll cost you $75,000 to create and it’ll cost you
$12,000 per month to support. If you hire a vendor they can build the solution for $63,000 but their solution will cost you $15,500 per month to support. How many months would you have to use your in-house solution to equate to the cost of the vendor’s solution?

 
 
 
 

NEW QUESTION 299
You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?

 
 
 
 

NEW QUESTION 300
You are the program manager for your organization. Management has asked you to create a method to track the program stakeholders’ concerns, threats, and demands for communication. They would like you to map out each stakeholder or stakeholder group and identify trends within the chart to help your program communicate better. What type of a chart should you create for management?

 
 
 
 

NEW QUESTION 301
Which of the following documents describes the details for each component in the WBS?

 
 
 
 

NEW QUESTION 302
Program manager B leaves the program and program manager A takes over the program responsibilities. Program manager A wants to ensure that all expected benefits of the program are realized.
What is used to assess the program cost/benefit justification?

 
 
 
 

NEW QUESTION 303
Your program has a budget at completion of $1,550,000 and is expected to last one year.
Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete at this, but due to some vendor delays your program is running just a bit late. Management is concerned that your program will not be able to recoup the costs of the expenses.
They’ve asked you to determine the cost variance for the program. What is the cost variance based on this information?

 
 
 
 

NEW QUESTION 304
You are the program manager for your organization and are working on gathering the requirements for a new solution and mission statement. There are several instances in the stakeholder pool where the stakeholders and their manager are being queried on possible requirements. You worry that the subordinates may have requirements, ideas, and suggestions to offer but they may be not submitting their thoughts because they do not want to contradict their managers. You believe you need a method to gather all requirements without the stakeholders having any fear of retribution. Which one of the following allows you to anonymously gather iterations requirements and still allow all stakeholders to review what has been submitted in an attempt to find consensus?

 
 
 
 

NEW QUESTION 305
Stakeholders ask the program manager to assess reasons for the project’s delay and provide a report. Also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget.
The program manager distributes information in accordance with which of the following?

 
 
 
 

The PgMP Multiple-Choice Exam

The last step is the multiple-choice exam. The multiple-choice questions’ problems are set and independently validated by a group of program management content experts worldwide.The set questions are based on the current program and project management titles and the PMI’s global standards.

Program management content experts confirm the PgMP exam questions using psychometric analysis, and it must satisfy the PgMP Exam Content Outline’s test specification.

 

PgMP PDF Dumps Are Helpful To produce Your Dreams Correct QA’s: https://www.actualtests4sure.com/PgMP-test-questions.html

         

By admin

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below