NO.62 Which of the following is NOT a tool or technique used to perform scope planning?

 
 
 
 

NO.63 Which of the following is not an internal stakeholder?

 
 
 
 

NO.64 Using the “normal” schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?

 
 
 
 

NO.65 What not only reflect an applicant’s financial situation and stability, they also provide other useful solution such as past addresses and previous employers?

 
 
 
 

NO.66 As the project plan is developed a mechanism is developed to communicate the projects organic structures that will facilitate reporting against the baseline schedule and cost estimate or budget Which of the following is NOT used for reporting?

 
 
 
 

NO.67 During proofing of the product manual, a problem was discovered requiring 15 days additional time to affect a correction. How can the date of availability be maintained?

 
 
 
 

NO.68 Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor’s baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

 
 
 
 

NO.69 Who will receive the most benefit from a master schedule of the Spring Highway project?

 
 
 
 

NO.70 What day would Activity C complete if the duration of Activity B was reduced to zero?

 
 
 
 

NO.71 Background
Your name is Evan Marshal. You are the corporate scheduler for Happy Insurance Corporation (HIC), a general health insurance company located in Ridgemond, Illinois. HIC is very busy with 49 unique software development projects. The organization structure at HIC gives the project scheduling responsibility to the Project Manager assigned to each project. You are charged with coordination of the project schedules into a Master Schedule and quality control for scheduling on the individual development projects. You report directly to the Director of Information Services (DIS), Desmond Rayburn.
It has come to your attention Project JP-114 has fallen behind schedule and Rita Belateau, the Project Manager, wants to accelerate the project in order to reclaim lost time. Rita is a strong supporter of Total Quality Management and strives for zero failures; therefore she is assessing the need for overtime for resources assigned to an activity that is not projecting a completion prior to the early finish depicted in the current schedule.
You and Rita review the current schedule to identify which activities are on the critical path and which activities have plenty of float. The review reveals several activities have suffered less than planned productivity and have contributed to falling behind. In the process of this review, you and Rita also review the budget for Project JP-114 and notice not only the schedule has fallen behind but the cost to date is more than she had expected. To total budget is $150,000, planned to date is $30,000; expended to date is $37,000.
With nine months remaining until baseline contract completion, Rita needs to bring Project JP-114 back on track; knowing overtime for an extended period of time is not always the right answer, especially with the cost to date already over planned.
In order to truly understand the options available to help remedy the current situation, you and Rita brainstorm on several potential courses of action. All the potential courses of action will require an evaluation of budget impact versus schedule correction.
1. Pull the project team together and ensure everyone understands which activities are on the critical path.
Rita would like to use the existing project team and focus them on these critical path activities, laying out a plan for periodic overtime when needed to crunch through a deliverable. This approach could add approximately 20% to the budget.
2. Outsource various modules of activities to qualified and known consultants. This could drive up the costs and must be evaluated before implemented. Having an outside source working in parallel with the project team could also accelerate the schedule to mitigate some of the delays, as well as keep overtime down to a minimum for the project team. Potentially this could add as much as 40% to the budget, but could also be very productive schedule wise.
3. Mandatory overtime for the project team – entire project goes on a 50-hour work week. If the entire project team works overtime for an extended period of time, the budget could see an additional 60% increase.
4. The project continues as is completes the project late and accepts the penalties imposed. Penalties imposed for late delivery could add as much as 50% to the budget.
Assignment
Draft a proper memorandum to Desmond Raybum, IS Director, explaining in your own words:
a. the current problem and potential impact(s);
b. each course of action, stating advantages and disadvantages as appropriate; c. your recommendations, properly supported.
Please be sure to include the rationale for your recommendations. Be sure to summarize your thoughts and address (To, From, Date, and Subject/Project Name) and close the memo appropriately. If you are uncomfortable with the courses of action noted, provide your own with appropriate substantiation for your position. Limit your answer to one, full typewritten page (roughly three handwritten pages).
While your email can be a detailed as you like, be sure to write sufficiently to address each element of the assignment, yet not so long that you go beyond the scope of the exercise.
Take time to read the problem and consider what you want Evan to say. Good luck!

NO.72 Identify the minimum project duration.

 
 
 
 

NO.73 Who developed Ethernet?

 
 
 
 

NO.74 As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

 
 
 
 

NO.75 During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

 
 
 
 

NO.76 Background
Your name is Evan Marshal. You are the corporate scheduler for Happy Insurance Corporation (HIC), a general health insurance company located in Ridgemond, Illinois. HIC is very busy with 49 unique software development projects. The organization structure at HIC gives the project scheduling responsibility to the Project Manager assigned to each project. You are charged with coordination of the project schedules into a Master Schedule and quality control for scheduling on the individual development projects. You report directly to the Director of Information Services (DIS), Desmond Rayburn.
It has come to your attention Project JP-114 has fallen behind schedule and Rita Belateau, the Project Manager, wants to accelerate the project in order to reclaim lost time. Rita is a strong supporter of Total Quality Management and strives for zero failures; therefore she is assessing the need for overtime for resources assigned to an activity that is not projecting a completion prior to the early finish depicted in the current schedule.
You and Rita review the current schedule to identify which activities are on the critical path and which activities have plenty of float. The review reveals several activities have suffered less than planned productivity and have contributed to falling behind. In the process of this review, you and Rita also review the budget for Project JP-114 and notice not only the schedule has fallen behind but the cost to date is more than she had expected. To total budget is $150,000, planned to date is $30,000; expended to date is $37,000.
With nine months remaining until baseline contract completion, Rita needs to bring Project JP-114 back on track; knowing overtime for an extended period of time is not always the right answer, especially with the cost to date already over planned.
In order to truly understand the options available to help remedy the current situation, you and Rita brainstorm on several potential courses of action. All the potential courses of action will require an evaluation of budget impact versus schedule correction.
1. Pull the project team together and ensure everyone understands which activities are on the critical path.
Rita would like to use the existing project team and focus them on these critical path activities, laying out a plan for periodic overtime when needed to crunch through a deliverable. This approach could add approximately 20% to the budget.
2. Outsource various modules of activities to qualified and known consultants. This could drive up the costs and must be evaluated before implemented. Having an outside source working in parallel with the project team could also accelerate the schedule to mitigate some of the delays, as well as keep overtime down to a minimum for the project team. Potentially this could add as much as 40% to the budget, but could also be very productive schedule wise.
3. Mandatory overtime for the project team – entire project goes on a 50-hour work week. If the entire project team works overtime for an extended period of time, the budget could see an additional 60% increase.
4. The project continues as is completes the project late and accepts the penalties imposed. Penalties imposed for late delivery could add as much as 50% to the budget.
Assignment
Draft a proper memorandum to Desmond Raybum, IS Director, explaining in your own words:
a). the current problem and potential impact(s);
b). each course of action, stating advantages and disadvantages as appropriate;
c). your recommendations, properly supported.
Please be sure to include the rationale for your recommendations. Be sure to summarize your thoughts and address (To, From, Date, and Subject/Project Name) and close the memo appropriately. If you are uncomfortable with the courses of action noted, provide your own with appropriate substantiation for your position. Limit your answer to one, full typewritten page (roughly three handwritten pages).
While your email can be a detailed as you like, be sure to write sufficiently to address each element of the assignment, yet not so long that you go beyond the scope of the exercise.
Take time to read the problem and consider what you want Evan to say. Good luck!

NO.77 If a contractor has robust planning and scheduling processes, should those company processes supersede client contract specifications?

 
 
 
 

ASIS Physical Security Professional (PSP) certification exam is a valuable credential for security professionals who are looking to enhance their career in security management. ASIS Physical Security Professional Exam certification exam validates the knowledge and expertise of security professionals in the field of physical security and demonstrates their commitment to the industry. With the right preparation and study, candidates can pass the exam and earn the PSP certification, which can open up new opportunities and career advancement in the field of physical security.

 

Certification Training for PSP Exam Dumps Test Engine: https://www.actualtests4sure.com/PSP-test-questions.html

         

Related Links: scalar.usc.edu qiita.com learn.csisafety.com.au www.slideshare.net www.intensedebate.com www.fanart-central.net

By admin

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below