Rate this post

Latest PK0-005 Exam Real Tests Free Updated Today

PK0-005 Real Exam Question Answers Updated [Aug 04, 2023]

To earn the CompTIA PK0-005 certification, candidates must pass a 90-minute exam consisting of 95 multiple-choice and performance-based questions. PK0-005 exam is available in various languages, including English, Japanese, Simplified Chinese, and Portuguese. Candidates can prepare for the exam by taking courses, studying textbooks, and practicing with sample questions.

CompTIA PK0-005 is a certification exam designed for professionals who are interested in project management. PK0-005 exam tests the candidates’ knowledge and skills in project management, including initiating, planning, executing, monitoring, controlling, and closing a project. It is an entry-level exam, which means that it doesn’t require any prior project management experience. However, it is recommended that candidates have some basic understanding of project management concepts before taking the exam.

 

NEW QUESTION 14
During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

 
 
 
 

NEW QUESTION 15
Which of the following is a test that is done on an existing system to ensure the previous functionality still works after a change has been made?

 
 
 
 

NEW QUESTION 16
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

 
 
 
 

NEW QUESTION 17
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

 
 
 
 

NEW QUESTION 18
Which of the following offers administrators more direct control over operating systems?

 
 
 
 

NEW QUESTION 19
Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

 
 
 
 

NEW QUESTION 20
A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?

 
 
 
 

NEW QUESTION 21
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

 
 
 
 

NEW QUESTION 22
A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

 
 
 
 

NEW QUESTION 23
As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

 
 
 
 

NEW QUESTION 24
A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?

 
 
 
 

NEW QUESTION 25
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

 
 
 
 
 

NEW QUESTION 26
Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

 
 
 
 

NEW QUESTION 27
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

 
 
 
 
 
 

NEW QUESTION 28
A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

 
 
 
 

NEW QUESTION 29
Which of the following BEST describes how an organization should coordinate management of multiple related projects?

 
 
 
 

Latest PK0-005 Study Guides 2023 – With Test Engine PDF: https://www.actualtests4sure.com/PK0-005-test-questions.html

         

By admin

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below